The main construction stages of «Gazprom center» are presented as construction site panoramic images.
-
28 August 2014
Preparation for construction
Preparation of the 8.27 ha site for construction: deconstruction of the buildings, facilities and utilities. In line with the green construction technology, all waste and materials made available in process re-used in accordance with city needs.
-
15 September 2014
Preparation of site continues
Total of 480 thou.m3 of soil excavated on site, exceeding excavation during construction of shopping mall «Stolica» in Minsk.
-
15 October 2014
Geotechnical survey in progress
Geotechnical survey launched.
-
2 November 2014
Disassembly complete
Site ready for construction work.
-
1 December 2014
Start of design work
Geotechnical survey complete, site levelled.
-
1 March 2015
Design «Stage A»
Temporary ring road construction. Start of pit excavation. Excavation depth - up to 20 m.
-
15 March 2015
Bentonite plant installation
Trenches filled with bentonite to prevent collapse of walls. Start of excavation shoring with diaphragm wall.
-
19 March 2015
Diaphragm wall
Construction of guide wall for the slurry.
-
25 March 2015
Diaphragm wall
Construction of guide wall for the slurry on site.
-
4 April 2015
Diaphragm wall
Diaphragm wall first panel construction.
-
23 April 2015
Diaphragm wall
Construction of guide wall for the slurry on the site.
-
30 April 2015
Diaphragm wall
Diaphragm wall first panel construction.
-
14 August 2015
Main phase of construction
Excavation works, pilot piles tested and installed.
-
18 October 2015
Main phase of construction
Pile work for high-rise building.
-
5 November 2015
Main phase of construction
Start of hotel and conference-centre construction. Preliminary base compaction and concrete blinding.
-
9 November 2015
Main phase of construction
Formwork of hotel base slab underway.
-
29 December 2015
Main phase of construction
Works underway to lay the foundation and substructure of hotel and conference centre.
-
22 January 2016
Main phase of construction
Pile cropping and HQ Tower groundwork in progress.
-
26 February 2016
Main phase of construction
HQ Tower pilework nearing completion; hotel and conference centre foundation works underway (2 underground floors).
-
23 March 2016
Main phase of construction
Start of ground slab construction (office building №6). Excavation works underway for power plant ground slab (back of house).
-
28 March 2016
Main phase of construction
HQ Tower pilework complete, start of HQ Tower base concrete construction. Ground slab construction for HQ Tower podium in progress.
-
3 May 2016
Main phase of construction
Ground slab pouring (buildings 3, 4, 5, 6).
3 May 2016
Main phase of construction
Work on power plant ground slab in progress.
3 May 2016
Main phase of construction
Construction of hotel and conference centre superstructure in progress.
-
24 May 2016
Main phase of construction
Main phase of construction - Ground slab for power plant administrative and amenity building complete.
-
10 June 2016
Main phase of construction
Hotel concrete frame construction (level 3, above ground).
-
13 June 2016
Main phase of construction
Ground slab reinforcement (commercial buildings 3, 4, 5).
-
15 July 2016
Main phase of construction
In-situ concrete being poured for power plant administrative and amenity building (underground level).
-
18 July 2016
Main phase of construction
In-situ concrete being poured for commercial buildings № 3, 4, 5, 6 (underground level).
18 July 2016
Main phase of construction
Hotel concrete frame construction underway (level 4, above ground).
-
4 August 2016
Main phase of construction
In-situ concrete poured on level 5 of hotel (1) and level 1 of conference - center (2).
-
5 August 2016
Main phase of construction
In-situ concrete being poured on underground level of commercial building №5 (pic. 2) and level 1 of power plant administrative and amenity building, concrete bedding for ground slab in progress (pic.1).