Construction progress

The main construction stages of «Gazprom center» are presented as construction site panoramic images.

  1. 28 August 2014
    Preparation for construction
    Preparation of the 8.27 ha site for construction: deconstruction of the buildings, facilities and utilities. In line with the green construction technology, all waste and materials made available in process re-used in accordance with city needs.
  2. 15 September 2014
    Preparation of site continues
    Total of 480 thou.m3 of soil excavated on site, exceeding excavation during construction of shopping mall «Stolica» in Minsk.
  3. 15 October 2014
    Geotechnical survey in progress
    Geotechnical survey launched.
  4. 2 November 2014
    Disassembly complete
    Site ready for construction work.
  5. 1 December 2014
    Start of design work
    Geotechnical survey complete, site levelled.
  6. 1 March 2015
    Design «Stage A»
    Temporary ring road construction. Start of pit excavation. Excavation depth - up to 20 m.
  7. 15 March 2015
    Bentonite plant installation
    Trenches filled with bentonite to prevent collapse of walls. Start of excavation shoring with diaphragm wall.
  8. 19 March 2015
    Diaphragm wall
    Construction of guide wall for the slurry.
  9. 25 March 2015
    Diaphragm wall
    Construction of guide wall for the slurry on site.
  10. 4 April 2015
    Diaphragm wall
    Diaphragm wall first panel construction.
  11. 23 April 2015
    Diaphragm wall
    Construction of guide wall for the slurry on the site.
  12. 30 April 2015
    Diaphragm wall
    Diaphragm wall first panel construction.
  13. 14 August 2015
    Main phase of construction
    Excavation works, pilot piles tested and installed.
  14. 18 October 2015
    Main phase of construction
    Pile work for high-rise building.
  15. 5 November 2015
    Main phase of construction
    Start of hotel and conference-centre construction. Preliminary base compaction and concrete blinding.
  16. 9 November 2015
    Main phase of construction
    Formwork of hotel base slab underway.
  17. 29 December 2015
    Main phase of construction
    Works underway to lay the foundation and substructure of hotel and conference centre.
  18. 22 January 2016
    Main phase of construction
    Pile cropping and HQ Tower groundwork in progress.
  19. 26 February 2016
    Main phase of construction
    HQ Tower pilework nearing completion; hotel and conference centre foundation works underway (2 underground floors).
  20. 23 March 2016
    Main phase of construction
    Start of ground slab construction (office building №6). Excavation works underway for power plant ground slab (back of house).
  21. 28 March 2016
    Main phase of construction
    HQ Tower pilework complete, start of HQ Tower base concrete construction. Ground slab construction for HQ Tower podium in progress.
  22. 3 May 2016
    Main phase of construction
    Ground slab pouring (buildings 3, 4, 5, 6).
    1/3
    3 May 2016
    Main phase of construction
    Work on power plant ground slab in progress.
    2/3
    3 May 2016
    Main phase of construction
    Construction of hotel and conference centre superstructure in progress.
    3/3
  23. 24 May 2016
    Main phase of construction
    Main phase of construction - Ground slab for power plant administrative and amenity building complete.
  24. 10 June 2016
    Main phase of construction
    Hotel concrete frame construction (level 3, above ground).
  25. 13 June 2016
    Main phase of construction
    Ground slab reinforcement (commercial buildings 3, 4, 5).
  26. 15 July 2016
    Main phase of construction
    In-situ concrete being poured for power plant administrative and amenity building (underground level).
  27. 18 July 2016
    Main phase of construction
    In-situ concrete being poured for commercial buildings № 3, 4, 5, 6 (underground level).
    1/2
    18 July 2016
    Main phase of construction
    Hotel concrete frame construction underway (level 4, above ground).
    2/2
  28. 4 August 2016
    Main phase of construction
    In-situ concrete poured on level 5 of hotel (1) and level 1 of conference - center (2).
  29. 5 August 2016
    Main phase of construction
    In-situ concrete being poured on underground level of commercial building №5 (pic. 2) and level 1 of power plant administrative and amenity building, concrete bedding for ground slab in progress (pic.1).